It’s Week 5 and I’m posting for the first time since Week 1. WHOOPS.

Kids, man. That’s my excuse. Between stomach viruses and biting issues I’m not sure we’ve gone a full week this month with all 3 kids in daycare. Could this week be the one? MAYBE! But I’ve also been exhausted this week and have gotten zero done.
Since my last post, we decided to keep the navy walls and just freshen them up with a new coat of paint. We’ve also decided to bring in some bright colors in other ways and scratch the beams (at least for now). This weekend we’ll be working on patching the wall where the old closet was and figuring out how we want to build our closet doors.
Here’s a tiny glimpse of a few of my favorite elements so far:



And here’s how our list is looking:
-Patch subfloor where closet was removed
-Finish installing new floors – In Progress
-Remove old sconces
-Patch drywall where necessary – In Progress
-Paint walls – In Progress
-Build faux beams
-Stain faux beams
-Install faux beams
-Install Pax wardrobes
-Build upper cabinets for above wardrobes
-Paint upper cabinets
-Install upper cabinets
-Build wardrobe doors
-Paint wardrobe doors
-Install wardrobe doors
-Buy light fixture
-Install light fixture
-New bed
-Install sconces
-Buy rug
-Trim out bedroom doors
-Paint bedroom doors
-Decorate
-If there’s time, build/paint/install bathroom doors
-Color project
I still think we can get it all done but our time has been limited so I’m hoping that changes for these last few weeks. Be sure to check out everyone else’s updated here.








































I’ll also need to go back and get into the mortar better in a few spots. Our mortar is pretty deep set and it’s been difficult to get good coverage using the masonry brush. I remembered afterward that we have a paint sprayer so I might try that out for the rest of the wall. I was hoping I could leave the door to the garage alone but after painting the brick, I don’t think the color is working. My plan is to find a light gray but the gutters and downspout will likely stay the same color unless I can’t stand it and then we’ll see what happens. The gutters also need to be cleaned ASAP.
We’re thinking we’re going to build a raised planter along the other wall (stained to match the deck) and plant some hostas to help hide the foundation and maybe help disguise our meters. Hopefully we can get that done during the ORC but it’s an extra project that wasn’t in our original plan.
We finished our deck expansion on Saturday with help from Kyle’s parents. Not sure if we’ll be able to get it stained by the end of the ORC but at least the building part is done!
Kyle installed some temporary stairs down into the yard for OG and the dogs but Phase 2 of this project will include adding some big box steps and railings to finish everything off.
We are still planning on building an outdoor fireplace at some point but that will also be a Phase 2 project and won’t be done during the ORC. We’re planning on going ahead and pouring a concrete pad for it when we rent the mixer for our pavers but the actual building and plastering we’ll save for later. There are still a lot of details to figure out there.
As for moving the gravel, we’ve gone back and forth on this but we decided to leave it all in place and just move it around as we need to. We have a lot of leveling to do this weekend since the patio is sloped about 6-8 inches and we’ll probably just use the gravel that’s there as a base layer and get marble chips to go on top and between the pavers instead of using the aggregate.
We also didn’t cut/cap any sprinklers because we’ve only come across one so far and it’s not in the way so we can deal with it later if we need to.
We did start leveling out the first concrete form but got rained out. It’s supposed to be nice most of this weekend so I’m hoping we can get a lot of leveling done and most, if not all, of the forms in place. We weren’t able to build anymore over the weekend so we’ll start by setting the 5 we have and go from there.
Here’s our plan for this weekend:
Then, before we could even start digging out holes for the new deck posts, we had an idea that ended up changing our entire plan: What if we built an outdoor fireplace? Not a fire pit, but an actual wood burning fireplace with a hearth and a chimney.
(Ignore the measurements)
How does that change our plan? Well, we don’t have enough space for the full deck expansion we had planned and the fireplace where we want it. The whole reason we were doing the deck expansion was so that we could eventually replace our dining room window with a sliding door that would lead out onto the deck. Moving the doors from the kitchen to the dining room would have given us enough space for 3 more sets of drawers and another 4.5ft of counter space in the kitchen. So we could either keep our original plan or we could add in the fireplace and scrap our plans to expand the kitchen and the deck.
In the end, we decided to scrap our original plans. We have plenty of storage in the kitchen and while we have slightly less counter space than I’d like to have, the island makes up for it. So instead of a full deck expansion, we are just adding on large box steps down into the new patio area and we’ll add another set down into the yard.
Now, I’m not thinking we’ll be able to build the fireplace in the time frame of the One Room Challenge. If we had this idea from the beginning and had started on time instead of two weeks late, I’d feel pretty confident, but we already have a huge list to get done and we’re battling the weather (remind me to never commit to an exterior project for the ORC again, mmmmkay?). Plus, we need HOA approval and I haven’t even submitted our request yet.
ANYWAY. We weren’t prepared for that change of plans and basically lost half of the weekend but we did get two of our new posts set before the rain hit (we’ll still need 4 posts for the steps we’re building).
We also ripped down a sheet of plywood to use for our concrete forms. We used 2x4s last time and that’s what I would rather use but we already had 2 sheets of plywood that were just sitting in our garage with no purpose so we’re using those up first. We ripped enough material to put together 7 forms (I think we need 14 for the pavers and we’ll need more for the concrete pads for the kitchen area and fireplace) and Kyle built 5 of the forms over the weekend.
We started playing around with the placement to make sure spacing will work.
On Monday, we got hit with crappy weather and it rained every day until Thursday.
We’re supposed to get more rain on Sunday so we’re hoping to get a little bit of work done after work today (Friday) and knock out the deck stairs with some assistance from Kyle’s dad tomorrow.
Here’s how it was looking near the end of the weekend (before we got our second post in):
Yikes. I can’t decide if that’s better or worse than how it looked a couple of years ago…
In better news, we got our approval from our HOA to paint our brick. I’ve been having the hardest time finding the limewash I want to use in stock due to the shutdowns in Italy but I managed to find a local paint store that carries it and has two of the color options in stock. The store also happens to be on my way home from work (my company recalled everyone to the office this week) and is offering curbside pick up so I’m going to swing by on my way home to pick up some to test out. Eventually we’d like to add brick around the rest of our foundation and maybe above the garage door around front and paint the siding white as well but those things will be done down the road.
Here’s what I’m hoping we can get done this weekend (majorly dependent on weather):





















